Our Pavaclad and Pavaroof systems require taping ONLY on butt joints,
corners or drip details. The
tongue and groove
board edges require no taping. For reference, please use our Technical Manuals.
- Only use PAVATAPE on dry, clean and dust-free Pavatex board
- Use after fitting boards and always BEFORE installing battens
- Two priming solutions are available dependent on weather conditions: For
temperatures between 5 - 10 degC use PAVZTP05 (solvent based) use
PAVZTP5 (water-based).
- PAVATAPE should not be applied if the
temperature is below 5 degC.
- Apply Pavatex PRIMER with a brush or roller onto the board and
abutments and allow to dry: Water-based 30 and 60 minutes drying time; solvent based
prime, 20min.
- Store Pavatex PAVATAPE rolls
on a flat surface in a dry dust-free environment.
- Shelf life when
stored at around 20 degC is unlimited for PAVATAPE. PRIMER needs to be
used within 12 month after manufacture.
- Coverage - Primers - Water based - 5litre tins, enough for 6 rolls of Pavatape. Solvent based - 500ml tins,
enough for 1 roll of Pavatape
- Pavatape comes in 150mm wide, 15m rolls.
NBT supply all fixings and fittings required for our systems - assuring quality and our warranty can be
applied.
We recommend Ejot and Fisher fixings for our Pavatex insulation boards - they are available
direct from us, and our representatives can advise on correct
quantities, tools etc.
Fixings